Current Projects
Vistara
4th Street and N. Haven Ave.
Ontario, CA 91764
Project Manager:
298 Units
3 Story Slab On Grade
Start Date: August 05, 2014
Architect: Architects Orange
Structural Engineer: Patel Burica & Associates, Inc.
Mechanical Engineer: LDI Mechanical, Inc.
Plumbing Engineer: TRYCO Consulting, Inc.
Electrical Engineer: RVM Engineering, Inc.
Landscape Architect: Urban Arena
Civil Engineer: Land Development Consultants
Soils Engineer: Albus-Keefe & Associates, Inc.
Appliances |
Asphalt Pavement |
Cabinets |
Cable TV Prewire |
Carports |
Clubhouse Cabinets |
Dry Utilities |
Drywall |
Electrical Wiring |
Erosion Control |
Fine Grading |
Finish Carpentry |
Fire Alarm |
Fire Sprinklers |
Fireproofing |
Framing Labor |
Gutters/Downspouts |
Gypcrete |
HVAC |
Insulation |
Landscaping |
Masonry Walls |
Metals |
|
Mirrors |
Overhead Garage Door |
Plumbing |
Quartz Countertops |
Resilient Flooring |
Roofing |
Rough Clean |
Security |
Sheet Metal |
Site Concrete |
Structural Concrete |
Structural Steel |
Stucco |
Surveying |
Swimming Pool |
Temporary Labor |
Temporary Power |
Tub/Shower Enclosure |
Waterproof Decking |
Wet Utilities |
Window Coverings |
Windows/Slding Doors |
|
Item |
Status |
% Complete |
12 |
Paint Punch, Punch & Detail Units, Punchlist Walk, Rough Clean |
1% |
15 |
C of O Received, Install Carpet, Punch & Detail Units, Drywall Punch and Patch |
1% |
16 |
Paint Punch, Install Carpet, Punch & Detail Units, Punchlist Walk |
1% |
3 |
Paint Punch, Window Coverings, Install Carpet, Punch & Detail Units |
1% |
4 |
Paint Punch, Window Coverings, Install Carpet, Appliance Installation |
1% |
5 |
Paint Punch, Tackstrip & Pad, Window Coverings, Install Carpet |
1% |
6 |
Punch & Detail Units, Punchlist Walk, Rough Clean, Drywall Punch and Patch |
1% |
7 |
Punch & Detail Units, Punchlist Walk, Drywall Punch and Patch, Misc Trim & Punch |
4% |
8 |
Paint Punch, Punch & Detail Units, Punchlist Walk, Rough Clean |
4% |
Activity |
Proposed Date |
Actual Date |
Project Start |
9/29/14 |
9/29/14 |
Clubhouse Turnover |
8/31/15 |
1-15-16 |
Phase 2 Completion |
8/31/15 |
3-11-16 |
Phase 3 |
9/30/15 |
3-25-16 |
Phase 4 |
10/30/15 |
4-3-16 |
Phase 5 |
12/1/15 |
4-27-16 |
Phase 6 |
1/12/15 |
6-8-16 |
Phase 7 |
2/26/16 |
7-6-16 |
Phase 8 |
3/29/16 |
7-27-16 |
Project Completion |
3/29/16 |
7-27-16 |