Current Projects
Citrus Grove
1120 North Lemon St.
Orange, CA 92867
Project Manager: Bill Bullock
57 Units
3 Story Slab On Grade
Start Date: January 08, 2010
Architect: Barry Adnams
Structural Engineer: RM Volpe & Associates
Mechanical Engineer: Gevork Consulting Engineers, Inc
Electrical Engineer: Gevork Consulting Engineers, Inc
Landscape Architect: Cathcart / Begin Associates, Inc
Civil Engineer: DMS Consultants Inc
Soils Engineer: LOR Geotechnical Group, Inc
| Appliances |
| Cabinets |
| Carpet |
| Carports |
| Concrete Curb/Gutter |
| Concrete Pavers |
| Countertops |
| Dry Utilities |
| Drywall |
| Electrical Fixtures |
| Electrical Wiring |
| Final Clean |
| Finish Carpentry |
| Fire Alarm |
| Fire Sprinklers |
| HVAC |
| Insulation |
| Lightweight Concrete |
|
| Masonry Walls |
| Metal Stairs |
| Painting |
| Plumbing |
| Roofing |
| Rough Carpentry |
| Rough Cleans |
| Rough Grading |
| Security Surveillnce |
| Sheet Metal |
| Sim. Stone Veneer |
| Solar Equipment 2 |
| Structural Concrete |
| Stucco |
| Tub/Shower Enclosure |
| Waterproof Decking |
| Wet Utilities |
| Windows/Slding Doors |
|
| Item |
Status |
% Complete |
| Demo |
Complete |
100% |
| Perimeter Walls |
Complete |
100% |
| Structural Concrete |
Complete |
100% |
| Wet Utilities |
In progress - currently installing Storm drain behind Building C |
100% |
| Dry Utilities |
In Progress |
100% |
| Drive Isles |
In progress - lime/concrete treated the soil and grading. |
100% |
| Framing |
In progress - Lumber Drop and first floors framed. Currently setting beams and joists. |
100% |
| Roofing |
In progress - Buildings are complete; carports are remaining |
90% |
| Drywall |
In Progress - Drywall stocked, installing prelim. |
100% |
| Texture |
Complete |
100% |
| Stucco/Stone Veneer |
Stucco Complete; Stone Veneer Complete |
100% |
| Landscape |
In Progress - Irrigation Complete, installing plant material |
70% |
| Site Concrete |
In Progress - Approx 80% Sidewalk complete; 90% of the carport slabs complete; 100% Curb & Gutter complete |
85% |
| Activity |
Proposed Date |
Actual Date |
| Precon / Kick-off |
1/11/10 |
1/11/10 |
| Certify Pads |
1/25/10 |
1/25/10 |
| Lumber Drop (if dirt framing) |
3/1/10 |
3/11/10 |
| MEPS for Last Building |
6/15/10 |
4/22/10 |
| C of O (Contractor's Proposed Date, 10 month schedule) |
11/11/10 |
|
| C of O (Contract Date, 12 month schedule) |
1/11/11 |
|