Current Projects
Greenleaf Family
2048 W Greenleaf Avenue
Anaheim, CA 92801
Project Manager: Adam Jacobsen
20 Units
2 Story Slab On Grade
Start Date: February 15, 2010
This Is A Prevailing Wage Project
Architect: Advent Design Group
Structural Engineer: Patel Burica & Associates, Inc.
Mechanical Engineer: TAD Consulting Inc.
Electrical Engineer: DGM & Associates
Landscape Architect: KLA, Inc.
Civil Engineer: Merit Civil Engineering, Inc.
| Appliances |
| Asphalt Pavement |
| Cabinets |
| Countertops |
| Drywall |
| Electrical Wiring |
| Fences & Gates |
| Final Clean |
| Finish Carpentry |
| Fire Sprinklers |
| Gutters/Downspouts |
| HVAC |
| Insulation |
| Landscaping |
| Lightweight Concrete |
|
| Masonry Walls |
| Mirrors |
| Painting |
| Plumbing |
| Resilient Flooring |
| Roofing |
| Rough Carpentry |
| Rough Grading |
| Site Concrete |
| Solar Equipment |
| Structural Concrete |
| Wet Utilities |
| Window Coverings |
| Windows/Slding Doors |
|
| Item |
Status |
% Complete |
| Flooring |
Carpet installation in progress. |
50% |
| Monument Sign |
Footing poured. |
20% |
| Stone Veneer |
Pending. |
0% |
| Landscaping |
Plant material to arrive Thursday 9/2/10 and Friday 9/3/10. |
0% |
| Appliances |
All have been delivered and are being installed. |
100% |
| Window Coverings |
Pending. |
0% |
| Trash Enclosures / Seat Walls |
In progress. |
0% |
| Photovoltaic |
Supports installed. Array work to begin on 9/2/10. |
15% |
| Site Concrete |
In progress. |
90% |
| Irrigation |
In progress. |
80% |
| Site Drains |
All underground complete. Grates pending landscaping. |
90% |
| Activity |
Proposed Date |
Actual Date |
| Start demolition / clearing / grading |
2/16/10 |
2/16/10 |
| Certify pads |
3/12/10 |
3/18/10 |
| Backfill retaining walls |
4/16/10 |
7/30/10 |
| Complete utilities (less gas) |
4/27/10 |
4/2/10 |
| Start Framing |
5/14/10 |
4/27/10 |
| Owner Box Walk (Comm. Ctr.) |
5/5/10 |
5/5/10 |
| Owner Box Walk (Units) |
5/12/10 |
5/12/10 |
| Ready to insulate |
6/25/10 |
6/9/10 |
| Complete curbs / gutters |
7/1/10 |
9/2/10 |
| Complete flatwork |
7/23/10 |
9/2/10 |
| Complete drywall |
7/26/10 |
7/3/10 |
| Complete landscaping |
8/20/10 |
|
| Install carpet |
8/30/10 |
|
| Pave parking lot |
8/31/10 |
|
| Owner's walk / management training |
9/7/10 |
|
| Certificate of Occupancy |
9/16/10 |
|
| Contractual completion date |
11/15/10 |
|